|

Folks restive over start of landfill
By
KIT BAGAIPO
Alburquerque
residents opposed to the hosting of a cluster sanitary landfill
are asking for the cessation of works now ongoing at the project
site.
Meanwhile,
Gov. Erico Aumentado reassured that he will not allow the
project to proceed further if his request for experts and
scientists in the field of sanitary landfills would not be
able to conduct dialogues with Albur residents.
Hugpong
Alburanon Nagpakabana (Hugalna) president Lourdes Pinlac told
the Chronicle yesterday that construction works at the cluster
sanitary landfill site in barangay Dangay started last Tuesday.
|
|
|
In
fact, the project's contractor started clearing operations
at the project site and were hiring workers for the
construction.
Pinlac
said Albur residents were "surprised and shocked"
when they learned that the Department of Environment
and Natural Resources (DENR) issued an environmental
compliance certificate (ECC) for the project.
The
ECC was issued October 10, 2007 by the DENR's Environmental
Management Bureau (EMB) Region 7 chief Alan Arranguez.
|
The
start of construction works is being challenged by Hugalna
as there are still requirements and queries posed by the group
on the project.
According
to Pinlac, the group opposed to the project may have to seek
a court order to stop the implementation of the project.
However,
a court action will be "a last resort", Pinlac said,
as they want to allow the governor and the project's proponents
to hear their pleas and cancel the cluster sanitary landfill
project.
The
project is being funded by the Philippine Tourism Authority
(PTA) as a component of the Panglao Island Tourism Estate
and the Panglao international airport project.
SOCIAL
ACCEPTABILITY
In
a letter to PTA General Manager Robert Dean Barbers and several
town mayors, Pinlac cited that the project's proposed site
at barangay Dangay violates Article 6, Sec. 40 of RA 9003,
the Ecological Solid Waste Management Act of 2000.
"The
area is one of the sources of potable water of Albur residents,"
she said.
Another
requirement of RA 9003 is social acceptability of the cluster
sanitary landfill project,
which according to Pinlac, is not achieved as "there
was no transparency and honesty in the conduct of information
dissemination inasmuch as the people were not asked whether
they are amenable or not to the establishment and hosting
of the cluster sanitary landfill."
Under
the memorandum of agreement (MOA) of the Albur cluster sanitary
landfill project (now named Metro Bohol Cluster Sanitary Landfill
Project) the town will host garbage from some 11 towns who
are signatories of the MOA.
However,
there is no assurance that only the 11 towns will be dumping
their wastes in Albur, according to Hugalna, as there have
been no other similar projects being planned in other towns.
The
DENR is mandated to close down all open dumpsites and waste
disposal facilities that do not qualify under RA 9003. Hence,
Hugalna fears that their town will become "the garbage
capital of Bohol."
'DECEPTION'
According
to Hugalna, they were "denied access" to documents
relative to the project.
Since September 2006, written requests were made by Hugalna
to former mayor Efren Tungol asking for the project proposal
and feasibility study, Environmental Impact Assessment (EIA),
the town's comprehensive land use plan (CLUP) and the Integrated
Solid Waste Management Plan (ISWMP).
However,
it was only after the May 14, 2007 elections when mayor Jose
Ugdoracion assumed office that they were able to get a copy
of the ISWMP.
"After
[getting a copy] of the ISWMP we found out that the said plan
is filled with inconsistencies and the data gave a false picture
of the municipality relative to the project," Hugalna
claimed.
Based
on the ISWMP, it was found that the local government unit,
"offered to host the cluster sanitary landfill"
through former mayor Tungol.
The
document also cited that Albur, a fifth class municipality,
generates some 4.2 tons of waste daily.
According
to Hugalna, the figure is "bloated" to justify the
offer of Albur to host the landfill.
The
ISWMP and the project's feasibility study presented by the
proponents included Tagbilaran City in the computation for
IRR despite the fact that it is not a signatory of the project
MOA since Tagbilaran City backed out from the cluster, Hugalna
said.
"This
is again another tactic to mislead and make the project appear
to be viable.
The
garbage from Tagbilaran City constitute about 85% of the total
garbage among the cluster members. Without Tagbilaran City,
it is very difficult to sustain the project," the group
argued.
Hugalna
also uncovered inconsistencies in the study made by the Mines
and Geo-sciences Bureau (MGB) regarding the project.
When
the town's Sangguniang Bayan (SB) requested for a copy of
the Initial Environmental Examination (IEE) of the project,
they learned that there is no IEE for the project.
An IEE is a requirement for the issuance of an ECC.
HIGH MAINTENANCE
Hugalna said a study on sanitary landfills constructed here
in the country shows that LGUs fail to sustain the project
due to its high maintenance costs.
Other sanitary landfills became open dump sites because the
government failed to sustain it, according to Hugalna.
The group cited the Bais and Clark Sanitary Landfill which
is the model of the Albur landfill.
The Bais landfill devolved into an open dumpsite because the
LGU of Bais had difficulty maintaining it after the German
support group completed the project, Hugalna claimed.
If the project fails in Albur, however, the group said it
will affect the source of potable water.
|