|
Insufficiency
of the much- needed water supply to fill Bayongan Dam, situated
in barangay Bayongan, San Miguel town may not serve well the
targeted 3,605 farmer-beneficiaries, who composed the 16 irrigator
associations of the towns of Ubay, San Miguel and Trinidad.
These
were the fears expressed by some sectors affected by the P3.6-billion
Bayongan Dam project, also known as the Bohol Irrigation Project
(BHIP) Stage 2.
In
an interview, former Gov. David B. Tirol told the Chronicle
that Bayongan Dam will be dependent on its water supply from
Malinao Dam, also known as Bohol Irrigation Project (BHIP)
stage 1, located in Pilar town.
Tirol
said that his 50-hectare rice field located within the covered
service area of Malinao Dam had already been leveled off into
rice paddies, hoping that it can avail of water supply. But
it appeared that his efforts came to naught because until
now, he said, the water did not literally reach his property
at barangay Estaca, Pilar town. He added that he already spent
some P2 million for the leveling of his lands.
In
an exclusive interview with the Chronicle, Tirol said that
"the leveling is correctly done. The elevation is the
proper elevation but the problem is sufficiency of supply
of water."
|
|
|
"He
should be the last person to say that. He is an engineer.
He knows elevation" Tirol told the Chronicle in
reaction to Engr. Membreve's statement blaming land
owners for the 'elevation problem.
Pressed
for further comments with regards to the fate of Bayongan
Dam of which viability depends on the spillover of excess
water from Malinao Dam, Tirol said "the least that
I could say about the matter, the better, kay daghan
ku'g ikasulti."
|
"The
success of the project depends on the ability of Malinao Dam
to spill excess water to Bayongan Dam," according item
No. 27 of the Project Evaluation Report of NEDA ICC, signed
by Roderick M. Planta, OIC director, PMS.
The
report quoted NIA's data that Malinao Dam could only irrigate
65% of the service area of some 4,900 hectares during wet
season and 53% during dry spell.
Non-government
organizations are quick to ask how can Malinao Dam supply
water to Bayongan Dam when it cannot even serve its target
clientele within its service area after its completion years
back?
Barangay
captain Demetrio Carnice Jr. of Los Angeles, Ubay town, who
also attended the inauguration last week estimated that Bayongan
Dam's water is only 30% and the 70% comes from Malinao Dam.
He said that it would only take two to three months for Bayongan
Dam water to supply the needed irrigation when long dry spell
hits the area.
Right
now, he said, Bayongan Dam attained only about 42 meters still
far from the desired 52 meters despite the onset of rainy
days.
For
his part, Janiel Golosino, president of the Bayongan-Capayas
Federation of Irrigators Association (BCFIA), described Bayongan
Dam as "rain-fed" and that 50% of its water is coming
from Malinao Dam.
He
said that NIA assured them (farmer-beneficiaries) that even
Bayongan Dam can have 50% water supply, still it can serve
the target beneficiaries. But he expressed apprehension that
they may be unable to pay the irrigation service fee (ISF)
of 300 kilos of palay per year to NIA when insufficiency of
water at Bayongan Dam occurs.
He
added that NIA won't collect ISF if the harvest will not yield
up to at least 40 sacks per cropping season but still they
would be served by Bayongan Dam.
Bayongan
has an existing 1,230 has. of rice paddies and still for leveling
are 2,910 has. within its target service area.
The
project has caused a controversy over the so-called cost overruns
or additional costs that exceed the original total project
cost. Funding of the project (BHIP stage 2) came from a loan
granted by Japan Bank for International Cooperation (JBIC)
to be paid for 25 years.
Former
NEDA secretary and now CHED commissioner Romulo Neri told
a TV program that the project (BHIP 2) cost overruns were
"excessive."
He
said NEDA will stand by its findings on the cost overruns
estimated at P1.2 billion, including the amount of P700 million
intended for the contractor's unpaid services.
Under
the same NEDA ICC report, Bayongan Dam is more high-priced
project compared to similar irrigation project. It said that
it cost the taxpayers some P684,882 to irrigate a hectare
of land. Bayongan Dam is "the most expensive irrigation
project being implemented by NIA," the ICC report said.
This
is higher than the P286,743 per hectare of land to be irrigated
under the Lower Agusan Development Project-Irrigation Component
(LADP-IC) and much higher than the P218,549 per hectare under
the Tarlac Groundwater Irrigation Systems Reactivation Project
(TGISRP).
LADP-IC
costs P2.272 billion and has a service area of 7,922 hectares.
(Ric Obedencio, Chito Visarra)
|